Project planning
Roadmap
- earlyOrganize in 2006 a Grid'5000 school where users can familiarize with scheduling/deploying tools
- 2005-11-14 : Opening to ACI Masse de Données, ACI Sécurité and possibly external communities for 2006 Grid'5000 Spring School
Décembre 2005
- Document rapport des expériences sur 9 mois pour négocier d’autres financements
- Evaluation à mi-parcours : inviter Michel Bidoit, Brigitte, Thierry, + 1 membre du comité scientifique de l’ACI Grid.
Réflexions
- Réflexions pour augmenter le budget : il faut atteindre au moins 500 CPUs par site pour obtenir les 5000 CPUs. Etablir d’ici fin 2005 un plan de demandes de financement : tous les responsables de sites
- à réfléchir au financement des interfaces 10 Gbps pour RENATER (20 K$) : tous les responsables de sites
What has been done so far
- Financial Supports
- "ACI Grid" with 2 calls for Grid'5000
- "ACI Masse de Données" with GriD eXplorer
- Local fundings (regions + departments)
- INRIA fundings
- 2 "AS CNRS" (Grid5000 and Grid Programming)
- Management and Internal Communication
- 1 Steering Committee + 1 Technical Committee
- Frequent audioconferences for each committee
- Wiki online interactive workspace
- Regular meetings with RENATER
- Public web site
- 1 Mailing list for each committee
- [...]
- 2005-06-xx : Assessment on the first 3 months of community usage
- 2005-11-14 : Wiki and public web site merged on a single portal
- Technical Achievements
- Grid prototype: 775 machines deployed over 9 sites
- Security prototype: operational VPN (VTUN)
- Control prototype: OAR
- Monitoring prototype: Nagios
- [...]
- 2005-03-15 : Automated WinXP launch (delay measurment)
- 2005-03-15 : Real size demos (> 1000 CPU)
- 2005-11-14 : Grid achievement: 1041 machines (2082 CPUs) deployed over 9 sites
- 2005-11-14 : Security achievement: dedicated VLAN (RENATER)
- 2005-11-14 : Control achievement: OAR + KaTools
- 2005-11-14 : Monitoring achievement: Monika, OARGantt, Ganglia, Nagios
- Partnerships
- 3 calls opened (CCTP written and approved by the Steering Committee)
- information exchange (Benchmarks, Costs, CPU availability, etc.)
- 2005-03-15 : 1Gb/s dedicated line between all Grid'5000 sites (RENATER)
- operational RENATER link for Grenoble
- RENATER probes available for Sophia, Grenoble, Rennes, Orsay, Toulouse (and soon Lyon)
- 3 calls opened (CCTP written and approved by the Steering Committee)
- Discussions and Brainstormings
- Operating modes: local clusters vs. Grid'5000
- User modes: shared, interactive, batch
- Demos: reboot, network, middleware, applications (call for permanent demos)
- Experiments census (and call for new proposals)
- Deadlines
- Partial scheduling ready for SC'04 demos (2004 November)
- Progressive prototype deployment up to 2004 October following a roadmap
- Switch to real equipment after 2004 October
- Opening to the full Grid'5000 community after 2005 January
- [...]
- 2005-03-15 : Opening to ACI Grid community as soon as possible
- 2005-06-xx : Opening to 2nd Plugtest for 2005 October
- External Communication
- see Grid5000:News section
- see Grid5000:Publications section
- see Grid5000:Press_releases section