Grid5000:Timeline: Difference between revisions
Jump to navigation
Jump to search
No edit summary |
|||
| (5 intermediate revisions by the same user not shown) | |||
| Line 4: | Line 4: | ||
==Project planning== | ==Project planning== | ||
[[Image: | [[Image:Grid5000_timeline.png|600px]] | ||
==Roadmap== | |||
*December 2005: Assessment on the first 9 months usage | |||
** Report to Funding Institutions Scientific Committees (Michel Bidoit, Brigitte Plateau, Thierry Priol & 1 ACI Grid member) | |||
** Brainstorming on how to budgetize at least 500 CPUs at each of the 9 sites (1000 for Orsay) to achieve the 5000 CPUs goal (some sites are already secured) | |||
** Brainstorming on how to budgetize 10 Gbps interfaces for RENATER (20 k$) | |||
*March 2006: Organize a Grid'5000 school where users can familiarize with scheduling/deploying tools | |||
** Opening to ACI Masse de Données & ACI Sécurité communities for the Spring School (reach stability) | |||
*Mid 2006: Opening to external communities and possibly "best effort" after first users reports | |||
==What has been done so far== | |||
=== Financial Supports === | |||
# "[http://www.recherche.gouv.fr/recherche/fns/grid.htm ACI Grid]" with 2 calls for Grid'5000 | |||
# "[http://www.recherche.gouv.fr/recherche/fns/mdonnees.htm ACI Masse de Données]" with GriD eXplorer | |||
# Local fundings (regions + departments) | |||
# INRIA fundings | |||
# 2 "AS CNRS" (Grid5000 and Grid Programming) | |||
=== Management and Internal Communication === | |||
# 1 Steering Committee + 1 Technical Committee | |||
# Frequent audioconferences for each committee | |||
# Wiki online interactive workspace | |||
# Regular meetings with RENATER | |||
# Public web site | |||
# 1 Mailing list for each committee | |||
# [...] | |||
* June 2005: Assessment on the first 3 months of community usage | |||
* November 2005: Wiki and public web site merged on a single portal | |||
== | === Technical Achievements === | ||
# Prototype: | |||
## Grid prototype: 775 machines deployed over 9 sites | |||
## Security prototype: operational VPN (VTUN) | |||
## Control prototype: OAR | |||
## Monitoring prototype: Nagios | |||
# [...] | |||
# Real size instrument: | |||
## Grid achievement: 1041 machines (2082 CPUs) deployed over 9 sites | |||
## Security achievement: dedicated VLAN (RENATER) | |||
## Control achievement: OAR + KaTools | |||
## Monitoring achievement: Monika, OARGantt, Ganglia, Nagios | |||
# March 2005: Automated WinXP launch (delay measurment) | |||
# March 2005: Real size demos (> 1000 CPU) | |||
=== Partnerships === | |||
# 3 calls opened (CCTP written and approved by the Steering Committee) | |||
## information exchange (Benchmarks, Costs, CPU availability, etc.) | |||
# March 2005: 1Gb/s dedicated line between all Grid'5000 sites (RENATER) | |||
## operational RENATER link for Grenoble | |||
## RENATER probes available for Sophia, Grenoble, Rennes, Orsay, Toulouse (and soon Lyon) | |||
=== Discussions and Brainstormings === | |||
# Operating modes: local clusters vs. Grid'5000 | |||
# User modes: shared, interactive, batch | |||
# Demos: reboot, network, middleware, applications (call for permanent demos) | |||
# Experiments census (and call for new proposals) | |||
=== Deadlines === | |||
* October 2004: Progressive prototype deployment following a roadmap | |||
* November 2004: Partial scheduling ready for SC'04 demos | |||
* December 2004: Switch to real equipment | |||
* January 2005: Opening to the full Grid'5000 community | |||
* March 2005: Opening to ACI Grid community as soon as possible | |||
* October 2005: Opening to 2nd Plugtest and prepare for SC'05 & PaRI-STIC | |||
* March 2005: Preparing the platform and tutorials for Grid'5000 winter school | |||
* October 2006: Preparing for SC'06, PaRI-STIC & 3rd Plugtest | |||
=== External Communication === | |||
Please have a look at: | |||
* The [[Grid5000:News|news]] section | |||
* The [[Special:G5KPublications|publications]] section | |||
* The [[Grid5000:Press_releases|press releases]] section | |||
Latest revision as of 19:08, 6 October 2006
Project planning
Roadmap
- December 2005: Assessment on the first 9 months usage
- Report to Funding Institutions Scientific Committees (Michel Bidoit, Brigitte Plateau, Thierry Priol & 1 ACI Grid member)
- Brainstorming on how to budgetize at least 500 CPUs at each of the 9 sites (1000 for Orsay) to achieve the 5000 CPUs goal (some sites are already secured)
- Brainstorming on how to budgetize 10 Gbps interfaces for RENATER (20 k$)
- March 2006: Organize a Grid'5000 school where users can familiarize with scheduling/deploying tools
- Opening to ACI Masse de Données & ACI Sécurité communities for the Spring School (reach stability)
- Mid 2006: Opening to external communities and possibly "best effort" after first users reports
What has been done so far
Financial Supports
- "ACI Grid" with 2 calls for Grid'5000
- "ACI Masse de Données" with GriD eXplorer
- Local fundings (regions + departments)
- INRIA fundings
- 2 "AS CNRS" (Grid5000 and Grid Programming)
Management and Internal Communication
- 1 Steering Committee + 1 Technical Committee
- Frequent audioconferences for each committee
- Wiki online interactive workspace
- Regular meetings with RENATER
- Public web site
- 1 Mailing list for each committee
- [...]
- June 2005: Assessment on the first 3 months of community usage
- November 2005: Wiki and public web site merged on a single portal
Technical Achievements
- Prototype:
- Grid prototype: 775 machines deployed over 9 sites
- Security prototype: operational VPN (VTUN)
- Control prototype: OAR
- Monitoring prototype: Nagios
- [...]
- Real size instrument:
- Grid achievement: 1041 machines (2082 CPUs) deployed over 9 sites
- Security achievement: dedicated VLAN (RENATER)
- Control achievement: OAR + KaTools
- Monitoring achievement: Monika, OARGantt, Ganglia, Nagios
- March 2005: Automated WinXP launch (delay measurment)
- March 2005: Real size demos (> 1000 CPU)
Partnerships
- 3 calls opened (CCTP written and approved by the Steering Committee)
- information exchange (Benchmarks, Costs, CPU availability, etc.)
- March 2005: 1Gb/s dedicated line between all Grid'5000 sites (RENATER)
- operational RENATER link for Grenoble
- RENATER probes available for Sophia, Grenoble, Rennes, Orsay, Toulouse (and soon Lyon)
Discussions and Brainstormings
- Operating modes: local clusters vs. Grid'5000
- User modes: shared, interactive, batch
- Demos: reboot, network, middleware, applications (call for permanent demos)
- Experiments census (and call for new proposals)
Deadlines
- October 2004: Progressive prototype deployment following a roadmap
- November 2004: Partial scheduling ready for SC'04 demos
- December 2004: Switch to real equipment
- January 2005: Opening to the full Grid'5000 community
- March 2005: Opening to ACI Grid community as soon as possible
- October 2005: Opening to 2nd Plugtest and prepare for SC'05 & PaRI-STIC
- March 2005: Preparing the platform and tutorials for Grid'5000 winter school
- October 2006: Preparing for SC'06, PaRI-STIC & 3rd Plugtest
External Communication
Please have a look at:
- The news section
- The publications section
- The press releases section